If a subcontractor or supplier serves a payment claim you can’t pay, the worst move is silence. In NSW you have 10 business days from receiving the claim, or less if your contract says so, to serve a written payment schedule. Miss that window and you’re on the hook for the full amount claimed. So: schedule what you genuinely owe, give every reason for the rest, and line up the money before the due date.
Most builders who end up in trouble with security of payment didn’t lose an argument. They lost a deadline. The claim arrived mid-pour, sat in an inbox, and by the time anyone looked at it the clock had run out.
This guide uses the New South Wales rules. Other states run their own versions with different timeframes, so check your project’s state and your contract.
How long do you really have?
Count business days, not calendar days, and count from when the claim reached you.
| Step | NSW deadline | What it means for your cash |
|---|---|---|
| Payment schedule | 10 business days after the claim, or sooner under the contract | Your one chance to dispute anything |
| Payment to a subbie on a commercial job | Due 20 business days after the claim, earlier if the contract says | The scheduled amount must be in their account by then |
| Payment from the principal to you | Due 15 business days after your claim, earlier if the contract says | The money you were counting on may land after your subbie’s due date |
| Adjudicated amount | 5 business days after the decision | No more negotiating, just paying |
| Suspension of work | After 2 business days’ notice if unpaid | The job stops and the delay is yours |
Those timeframes come from the NSW Government’s key deadlines summary, which also notes that a schedule “is only valid if provided within the set periods”. Your contract can set shorter periods. It can’t make them longer.
One more trap. If no schedule arrives and the due date passes, the claimant can give notice that it intends to apply for adjudication. You then get a further 5 business days to serve a schedule. Treat that as a lifeline, not a plan.
What happens if you just don’t respond?
It gets expensive, fast.
Under the NSW rules, if you don’t serve a payment schedule and don’t pay, “you are liable for the full amount claimed” (NSW Government). The claimant can then go to court for the full amount as a debt, or start adjudication. Either way, you can’t fall back on the contract defences or cross-claims you’d normally argue.
From there, the escalation looks like this:
- Suspension. After 2 business days’ warning, the claimant can down tools. It isn’t liable for your losses while it’s off site.
- A payment withholding request. Once the claimant has applied for adjudication, it can serve a request on whoever engaged you. That principal must hold back money it owes you, up to the amount claimed (NSW Government). Your own progress payment freezes.
- A judgment debt. An unpaid adjudicated amount can be turned into a court judgment through an adjudication certificate, then enforced like any other judgment (NSW Government).
- A statutory demand. For a company, an unpaid judgment often becomes a statutory demand. That starts a separate 21-day clock with the company’s survival at stake.
A claim worth a few weeks’ margin can end up threatening the whole business. That’s why the first ten days matter so much.
The 10-day plan when the money isn’t there
Day 0: stamp it and count. Note the date and time the claim arrived and how it was served. Check your contract for a shorter response period. Diary business day 10, and day 8 as your real deadline.
Day 1–3: value it honestly. Walk the work. Compare the claim with the contract, variations and your own records. Sort every line into three piles: owed, partly owed, genuinely disputed. Be ruthless here. A disputed item needs a real reason you can write down. “Cash is tight” isn’t a reason.
Day 3: line up the money for what you owe. The amount you’ll schedule is the amount you’ll need to pay. Work out the gap between that figure and what’s in the account on the due date, including any progress payment you’re expecting from the principal.
Payment claim landed and the account won’t cover it? Tell us the claim amount and your due date. It takes about 60 seconds, and a specialist calls you back.
Day 4–9: serve a proper schedule. In writing, addressed to the claimant, identifying the claim, stating the amount you’ll pay (even if it’s nil) and every reason for paying less. Attach your working, including how you valued anything you’re withholding. Reasons you leave out now can be very hard to rely on later. Serve it in a way you can prove.
By the due date: pay what you scheduled. On time, to the right account, with a remittance that matches the schedule. Paying the scheduled amount late can trigger suspension and adjudication all the same.
Should you dispute it or fund it?
Both, usually. Dispute what’s genuinely wrong. Fund what’s genuinely owed.
The mistake is using the dispute to buy time on money you know you owe. Security of payment is designed as a fast, interim process that keeps cash moving down the contracting chain. Adjudicators decide quickly on the papers in front of them. A builder who schedules nil on work that’s plainly done tends to end up paying the full amount anyway, five business days after the decision, with costs on top and a subbie who won’t come back.
The other mistake is borrowing to pay a claim you don’t owe. If the defects are real and documented, schedule them out. Funding is for the gap between what you owe and what you have.
Which funding fits a payment claim deadline?
It depends on the amount and how soon the due date falls. Our guide on how fast each type of business funding moves has the detail. In short:
- Up to $250k, due within days: an unsecured or cash flow loan sized on your bank statements and turnover can settle the same day in some cases. Good for a single claim when the principal’s payment is coming.
- Larger amounts, or several subbies at once: a property-secured loan, such as a caveat loan or second mortgage, can fund up to $5m within 24–48 hours. That suits a builder facing a cluster of claims at the end of a stage.
- A recurring gap between principal and subbie due dates: a line of credit or a longer-term facility, put in place once the immediate claim is paid.
Whichever route, know how you’ll repay it. That’s usually the principal’s next progress payment, the retention release or practical completion. Our cash flow loans page explains how lenders size those facilities for trades businesses.
Example: a fit-out builder with a stage-end crunch
This is an illustration, not a client story. A commercial fit-out builder in western Sydney is finishing stage two of an office refit. The electrical subcontractor serves a payment claim on a Tuesday afternoon. The builder agrees most of it is owed but disputes one variation and some rectification work.
The developer’s progress payment to the builder is running late, and the account won’t cover the agreed portion by the due date.
On day 2, the builder’s site manager walks the job and values the disputed items with photos. On day 3, the owner makes a funding enquiry with recent bank statements, the claim and the subcontract. On day 6, the builder serves a payment schedule paying the agreed amount and giving detailed reasons, with photos, for withholding the rest.
A short-term cash flow loan settles the following week, well inside the due date. The scheduled amount is paid in full and on time. The sparkies stay on site. The disputed variation is sorted out later, at a site meeting rather than in adjudication. The loan is repaid when the developer’s payment arrives.
The difference: a schedule served early, and money arranged before anyone asked for it.
A few things never to do
- Don’t ignore a claim because it “doesn’t look formal”. If it’s a valid claim under the Act, the clock runs anyway. Get advice if you’re unsure.
- Don’t serve a schedule that just says “disputed”. Reasons matter, and missing ones can cost you.
- Don’t promise payment you can’t fund. Missing the scheduled amount opens the door to suspension and adjudication.
- Don’t pay one subbie with money you owe another. That just moves the claim, and the deadline, down the list.
- Don’t let it reach a statutory demand. By then the conversation is about the company’s survival, not one invoice.
Keep the job moving: see if you qualify
A payment claim is a deadline that won’t move. Building has always been a business of paying out before you’re paid. We fund subcontractor claims, adjudicated amounts and stage-end crunches for builders all the time, and an ATO debt or an untidy credit file doesn’t make us hang up.
Here’s what happens when you get in touch:
- Sixty seconds, no credit check. Filling in the enquiry doesn’t touch your credit file.
- No spray and pray. Your details don’t get blasted out to a pile of lenders, so you won’t be fielding calls from strangers while you’re trying to run a site.
- One real person on your file. They look at the claim, the due date, when the principal is likely to pay and how the business trades, then ring you with a plan.
- Accurate answers win time. Put in the true claim amount and the true due date. It’s how we pick the right lender on the first go instead of the third.
Funding for a trading builder runs from $20k to $250k, and same-day settlement is sometimes possible. Where there’s property to offer as security, amounts up to $5m can be in place in 24–48 hours. Business purposes only. For more on how we work with the trades, see our page for builders and tradies.
The clock, step by step
- Day 0 Claim arrives: date-stamp it and diary business day 10
- Day 1–3 Check the work on site and value what's genuinely owed
- Day 3 60-second funding enquiry for the amount you'll schedule
- Day 4–9 Serve a written payment schedule with every reason for withholding
- Due date Funds land; scheduled amount paid; keep proof of payment
Questions we get asked
What happens if I don't respond to a payment claim in NSW?
If you don't serve a valid payment schedule in time and don't pay, you become liable for the full amount claimed. The claimant can sue for it as a debt, or start adjudication, and you lose the chance to rely on contract defences or cross-claims in those proceedings. A late or vague schedule can be almost as bad as none.
Can I get a business loan to pay a payment claim or adjudication amount?
Yes. Paying a subcontractor or supplier is a business purpose, and it's a common reason builders call us. Trading businesses can borrow $20k to $250k, possibly the same day. With property as security, up to $5m is possible within 24–48 hours. ATO debt or patchy credit doesn't automatically rule you out.
Can a subcontractor stop work if I don't pay?
Yes. In NSW, if you don't pay the scheduled, claimed or adjudicated amount on time, the claimant can suspend work after giving 2 business days' notice, and isn't liable for your losses from the suspension. Work must resume within 3 business days once the full amount is paid.
Can my subbie get paid out of money the developer owes me?
Potentially. Once a NSW claimant has applied for adjudication, it can serve a payment withholding request on whoever engaged you. That principal must then hold back money it owes you, up to the amount claimed, until the claim is paid or another ending event occurs. Your next progress payment can freeze at the worst moment.
If I pay the adjudicated amount, have I lost the argument?
Not necessarily. Security of payment is built as a fast, interim process to keep cash moving down the chain. Paying an adjudicated amount doesn't stop you pursuing the underlying dispute under the contract later. What you can't usually do is hold the money back while you argue.
Are the deadlines the same in Queensland, Victoria and other states?
No. Every state and territory has its own security of payment law, with different timeframes and forms. This guide uses the NSW deadlines. If the project is elsewhere, check that state's Act and regulator page, and read your contract, which can shorten the response time.
Does enquiring about funding affect my credit score?
No. There's no credit check when you first enquire. A real person reviews the claim, your deadline and how the business trades, then calls you before anything goes further.